Having somewhat changed the design, we have sent the plans regarding the foundations to an engineer, we are now waiting for a reply as to what they feel we should change or elements that will work as they are.  

The core original Chime group are also currently discussing which kind of structure to use for the overall main body one option is to have angled poles holding the different layers together. The detail group are waiting for a decision from the core group so that they can begin to make final CAD drawings which they will in turn send to the contractor to cut the wood. 

As far as the other details are coming along, at this point the bells have been purchased and we are awaiting delivery. The parts for the legs are here and will be constructed this week after which the bells will be added. The pulley system and bell mechanisms have been finalised and are ready to be made this week. 


                                                         